Virtual Open House: Central Chaplin – Leaside

Metrolinx and Crosslinx open houses are an opportunity to get project updates, to learn more about a specific topic of interest to you, and to ask general questions.

As we have shifted to virtual open houses, you can find below a project update presentation deck and video of this Autumn’s Central Chaplin – Leaside open house. 

You can also download the presentation PDF below. You can also view the materials and questions from the previous Central Works virtual open house.

Note: We will work to ensure questions are answered within 3-5 business days.

image of presentation pdf panel

Question submission closed on Tuesday, Oct 27, 2020.

Questions not related to this presentation? You can submit them via the ‘Contact Us’ form.

NOTE: Conduct inconsistent with our policies will result in the removal of your submission.

Comment Sort

Comments

Metrolinx's avatar

Metrolinx
Oct 22, 2020 - 15:43

Construction at each station will wrap up at different times. For example, By the end of 2020, three stations – Mount Dennis, Keelesdale and Science Centre – will be largely complete. Many other station areas will start to look complete in 2021, as finishing works and road restoration are underway.

Anonymous's avatar

Anonymous
Oct 24, 2020 - 00:21

How many LRVs have been delivered to the EMSF at Mount Dennis to date?

Metrolinx's avatar

Metrolinx
Oct 26, 2020 - 12:32

20 vehicles have been delivered to the EMSF.