New Track & Facilities - Environmental Project Report
The Environmental Project Report (EPR) has been completed for the New Track and Facilities TPAP, in accordance with Ontario Regulation 231/08.
The environmental impact of the New Track and Facilities transit project was assessed and an Environmental Project Report (EPR) was prepared in accordance with the Transit Project Assessment Process (TPAP) as prescribed in Ontario Regulation 231/08 - Transit Projects and Metrolinx Undertakings (made under the Environmental Assessment Act). The EPR for the New Track and Facilities was available for a 30-day public review period starting December 30 2020 – January 28, 2021 . The EPR is now being reviewed by the Minister of the Environment, Conservation and Parks.
The EPR and associated technical reports can be viewed below.
New Track and Facilities: Environmental Project Report
New Track and Facilities: Environmental Project Report - Executive Summary
New Track and Facilities: Environmental Project Report -Chapter 1
New Track and Facilities: Environmental Project Report -Chapter 2
New Track and Facilities: Environmental Project Report -Chapter 3
New Track and Facilities: Environmental Project Report -Chapter 4
New Track and Facilities: Environmental Project Report -Chapter 5
New Track and Facilities: Environmental Project Report -Chapter 6
New Track and Facilities: Environmental Project Report -Chapter 7
New Track and Facilities: Environmental Project Report -Chapter 8
New Track and Facilities: Environmental Project Report -Chapter 9
Appendices
APPENDIX A1 - Conceptual Corridor Plans
APPENDIX A2 - Conceptual Layover Facility & Storage Yard Plans
APPENDIX A3 - Proposed Switch Locations
APPENDIX B1 - Natural Environment Baseline Conditions Report
APPENDIX B2 - Natural Environment Impact Assessment Report
APPENDIX C1 - Hydrogeology Baseline Conditions Report - Part 1 of 4
APPENDIX C1 - Hydrogeology Baseline Conditions Report - Part 2 of 4
APPENDIX C1 - Hydrogeology Baseline Conditions Report - Part 3 of 4
APPENDIX C1 - Hydrogeology Baseline Conditions Report - Part 4 of 4
APPENDIX C2 - Hydrogeology Impact Assessment Report - Part 1 of 4
APPENDIX C2 - Hydrogeology Impact Assessment Report - Part 2 of 4
APPENDIX C2 - Hydrogeology Impact Assessment Report - Part 3 of 4
APPENDIX C2 - Hydrogeology Impact Assessment Report - Part 4 of 4
APPENDIX D1 - Land Use and Socio-Economic Baseline Conditions Report
APPENDIX D2 - Land Use and Socio-Economic Impact Assessment Report
APPENDIX E1 - Visual Baseline Conditions Report
APPENDIX E2 - Visual Impact Assessment Report
APPENDIX G1 - Archeological Baseline Conditions Report
APPENDIX G2 - Stage 1 Archaeological Assessment Report
APPENDIX H - Preliminary Stormwater Management Assessment Reports
APPENDIX I - Traffic Impact Assessment Reports
APPENDIX J – Third-Party Utilities Impact Assessment Report
APPENDIX K - Noise and Vibration Facilities Construction Impact Assessment Report
APPENDIX L - Air Quality Facilities Construction Impact Assessment Report
APPENDIX M1 - Richmond Hill Corridor Operational Noise & Vibration Assessment
APPENDIX M2 - Richmond Hill Corridor Operational Air Quality Assessment
APPENDIX N - Electromagnetic Interference/Electromagnetic Fields (EMI/EMF) Impact Assessment Report
APPENDIX O - Environmental Site Assessment Summary
APPENDIX P - Consultation Record
APPENDIX P1- Stakeholder Contact List
APPENDIX P2- Public Notices & Newspaper Ads
APPENDIX P3- Stakeholder Notifications & Correspondence
APPENDIX P4-Public Meeting Summary Report 1 - Part 1 of 4
APPENDIX P4-Public Meeting Summary Report 1 - Part 2 of 4
APPENDIX P4-Public Meeting Summary Report 1 - Part 3 of 4
APPENDIX P4-Public Meeting Summary Report 1 - Part 4 of 4
APPENDIX P5- Public Meeting Summary Report 2 -Part 1 of 8
APPENDIX P5- Public Meeting Summary Report 2 -Part 2 of 8
APPENDIX P5- Public Meeting Summary Report 2 -Part 3 of 8
APPENDIX P5- Public Meeting Summary Report 2 -Part 4 of 8
APPENDIX P5- Public Meeting Summary Report 2 -Part 5 of 8
APPENDIX P5- Public Meeting Summary Report 2 -Part 6 of 8
APPENDIX P5- Public Meeting Summary Report 2 -Part 7 of 8
APPENDIX P5- Public Meeting Summary Report 2 -Part 8 of 8
APPENDIX P6 - Public Meeting Summary Report 3- Part 1 of 2
APPENDIX P6 - Public Meeting Summary Report 3- Part 2 of 2
APPENDIX P7-Public Correspondence
APPENDIX P8- Indigenous Communities Consultation
APPENDIX P9- Municipal Consultation - Part 1 of 4
APPENDIX P9- Municipal Consultation - Part 2 of 4
APPENDIX P9- Municipal Consultation - Part 3 of 4
APPENDIX P9- Municipal Consultation - Part 4 of 4
APPENDIX P10- Review Agencies Consultation
APPENDIX P11- Elected Official Consultation - Part 1 of 5
APPENDIX P11- Elected Official Consultation - Part 2 of 5
APPENDIX P11- Elected Official Consultation - Part 3 of 5
APPENDIX P11- Elected Official Consultation - Part 4 of 5
APPENDIX P11- Elected Official Consultation - Part 5 of 5
APPENDIX P12- Other Organisations Consultation
For more information on the TPAP process and the Minister’s Review, please visit the following Government of Ontario webpages: