The Hurontario Light Rail Transit Project

The Hurontario LRT - Mississauga North

Neighbourhood Work Zone 

Construction for the Hurontario LRT in Mississauga North is separated into five work zones. Work zone 10 starts at Eglinton Avenue, ending at Matheson Boulevard, work zone 11 continues from there until Britannia, zone 12 continues to Madill Boulevard, work zone 13 stops at Derry and work zone 14 ends at Highway 407.

Work zone 9-12 along Hurontario Street between Square One Drive and Madill Boulevard.

Work zone 12 – 14 along Hurontario Street between Britannia Road and Highway 407 south ramp.

Major Construction Look Ahead, 2021

ZoneActivityStatus

Eglinton Avenue to Matheson Boulevard Work Zone 10

Next phase of utility relocation and roadway work begins Fall 2021. This work is anticipated to be complete by early 2023

Utility Relocation

  • West Side of Hurontario Street

Roadwork

  • Excavation, Removal and Disposal of Existing Roadway
  • Construction of New Roadway, Curbs & Sidewalks
  • Construction of Retaining/Gravity Walls

Matheson Boulevard to Britannia Road Work Zone 11

Utility relocation on the east side of Hurontario starting in late 2020, followed closely by road work. Track work and construction for stops at Britannia and Matheson will begin Summer 2021.

Utility Relocation

  • East and West Side of Hurontario Street

Roadwork

  • Excavation, Removal and Disposal of Existing Roadway
  • Construction of New Roadway, Curbs & Sidewalks
  • Construction of Retaining/Gravity Walls

Britannia Road to Capston/World Drive Work Zone 12

The next phase of utility relocation will begin on the west side of Hurontario in early 2021, at the same time as road work. Track work will follow in the Spring. This work is anticipated to be complete by Fall, 2021.

Utility Relocation

  • East and West Side of Hurontario Street

Roadwork

  • Excavation, Removal and Disposal of Existing Roadway Construction of New Roadway, Curbs & Sidewalks Construction of Retaining/Gravity Walls and track work

Capston/World Drive to Derry Road Work Zone 13

Road work will begin in late 2020, followed by the relocation of existing utilities in early 2021. Construction at the Courtneypark stop will begin early 2021, with track work starting in early 2022. This work is anticipated to be complete by Spring, 2022.

Utility Relocation

  • East and West Side of Hurontario Street

Roadwork

  • Excavation, Removal and Disposal of Existing Roadway Construction of New Roadway, Curbs & Sidewalks Construction of Retaining/Gravity Walls and track work

Derry Road to Mississauga/Brampton Boundary Work Zone 14

Next phase of utility relocation will begin on the West side of Hurontario Street in Fall 2020, along with major road work. Track work will begin Summer 2021. This work is anticipated to be complete in Fall, 2021.

Utility Relocation

  • East and West Side of Hurontario Street

Roadwork

  • Excavation, Removal and Disposal of Existing Roadway
  • Construction of New Roadway, Curbs & Sidewalks
  • Construction of Retaining/Gravity Walls