The Hurontario LRT - Mississauga North
Neighbourhood Work Zone
Construction for the Hurontario LRT in Mississauga North is separated into five work zones. Work zone 10 starts at Eglinton Avenue, ending at Matheson Boulevard, work zone 11 continues from there until Britannia, zone 12 continues to Madill Boulevard, work zone 13 stops at Derry and work zone 14 ends at Highway 407.
Major Construction Look Ahead, 2021
Zone | Activity | Status |
---|---|---|
Eglinton Avenue to Matheson Boulevard Work Zone 10 | Next phase of utility relocation and roadway work begins Fall 2021. This work is anticipated to be complete by early 2023 | Utility Relocation
Roadwork
|
Matheson Boulevard to Britannia Road Work Zone 11 | Utility relocation on the east side of Hurontario starting in late 2020, followed closely by road work. Track work and construction for stops at Britannia and Matheson will begin Summer 2021. | Utility Relocation
Roadwork
|
Britannia Road to Capston/World Drive Work Zone 12 | The next phase of utility relocation will begin on the west side of Hurontario in early 2021, at the same time as road work. Track work will follow in the Spring. This work is anticipated to be complete by Fall, 2021. | Utility Relocation
Roadwork
|
Capston/World Drive to Derry Road Work Zone 13 | Road work will begin in late 2020, followed by the relocation of existing utilities in early 2021. Construction at the Courtneypark stop will begin early 2021, with track work starting in early 2022. This work is anticipated to be complete by Spring, 2022. | Utility Relocation
Roadwork
|
Derry Road to Mississauga/Brampton Boundary Work Zone 14 | Next phase of utility relocation will begin on the West side of Hurontario Street in Fall 2020, along with major road work. Track work will begin Summer 2021. This work is anticipated to be complete in Fall, 2021. | Utility Relocation
Roadwork
|