> The Hurontario LRT - Brampton South | Metrolinx Engage

The Hurontario Light Rail Transit Project

The Hurontario LRT - Brampton South

Neighbourhood Work Zone

South is separated into two work zones. Work zone 15 starts at Highway 407, ending at County Court Boulevard, work zone 16 continues from there to Bartley Bull Parkway.

Image of work zones 14-16 along Hurontario Street between Derry to Bartley Bull.

Major Construction Look Ahead, 2021

ZoneActivityStatus

Mississauga Boundary to County Court Blvd Work Zone 15

Utility relocation and road work begins Fall 2021 with an anticipated completion of Fall 2022

Relocation of Existing Utilities

  • East and West Side of Hurontario Street

Roadwork

  • Excavation, Removal and Disposal of Existing Roadway
  • Construction of New Roadway, Curbs & Sidewalks
  • Construction of Retaining/Gravity Walls

County Court Boulevard to Bartley Bull Drive Work Zone 16

Utility relocation and road work begins Fall 2021. In parallel work begins to construct Brampton Gateway and County Court stops. Work is anticipated to be complete by early 2023

Relocation of Existing Utilities

  • West Side of Hurontario Street

Roadwork

  • Excavation, Removal and Disposal of Existing Roadway
  • Construction of New Roadway, Curbs & Sidewalks
  • Construction of Retaining/Gravity Walls