Eglinton Crosstown LRT - Virtual Open House - West - Mount Dennis Station to Avenue Station

Metrolinx and Crosslinx open houses are an opportunity to get project updates, to learn more about a specific topic of interest to you, and to ask general questions.

As we have shifted to virtual open houses, you can find below a project update presentation deck of this Fall’s Mount Dennis Station to Avenue Station open house. 

You can also download the presentation PDF below. 

Note: There is no real-time engagement during the open house. We will work to ensure questions are answered with 3-5 business days.


 

image of presentation pdf panel

 

Submit your questions about the presentation below. Question submission will close on November 10, 2021.

Questions not related to this presentation? Please contact us.

NOTE: Conduct inconsistent with our policies will result in the removal of your submission.

Comment Sort

  • Sort questions:
  • Date
  • Popularity

Comments

Anonymous's avatar
Nov 3, 2021 - 19:36

1) What is the current schedule for the completion of this project, i.e. when will the first riders be using the LRT. I understand that schedules can be changed. The implication of the slides is that everything will be completed in 2022. Is that correct?

2) Has the testing been generally acceptable or have there been any significant issues

  • Vote for this question10
  • Downvote this question1
Metrolinx's avatar

Metrolinx
Nov 9, 2021 - 16:15

That is correct, the project is currently tracking for completion in 2022, when service operated by TTC can begin.

Train testing is meeting expectations and will continue throughout 2022.

  • Vote for this question0
  • Downvote this question0
Anonymous's avatar
Nov 5, 2021 - 09:55

Since no exact date has been specified, it seems clear the opening will be pushed to 2023. When will this be publicly acknowledged, or when will an estimated month be set?

  • Vote for this question8
  • Downvote this question0
Metrolinx's avatar

Metrolinx
Nov 11, 2021 - 09:06

The project is still currently tracking for completion in 2022, but a specific month or date has not yet been announced. When that information becomes available it will be widely publicized.

  • Vote for this question0
  • Downvote this question0
Anonymous's avatar

When do you expect the roads in the area of Cedarvale and Forest Hill stations to be restored to their full width? When will turn restrictions and one-way roads be returned to the previous set up? Thanks.

  • Vote for this question6
  • Downvote this question1
Metrolinx's avatar

Metrolinx
Nov 9, 2021 - 16:18

Road restoration and landscaping at both Cedarvale and Forest Hill Stations is scheduled for 2022, though a more specific timeline has not been shared. Sign up to receive notices by email to find out when new construction activities are announced for these stations: http://thecrosstown.ca/sign-up

Road restoration will be followed by the conclusion of turn restrictions and lane reductions. 

  • Vote for this question0
  • Downvote this question0
Anonymous's avatar

You indicated to another individual that "the project is currently tracking for completion in 2022" Can you please provide a more direct answer for all of us. We as tax payers have spent billions on this project so the least we can expect is a direct answer. Plz answer saying which month the LRT will open. Please answer in this format Month, 2022

  • Vote for this question4
  • Downvote this question0
Metrolinx's avatar

Metrolinx
Nov 11, 2021 - 09:06

The project is still currently tracking for completion in 2022, but a specific month or date has not yet been announced. When that information becomes available it will be widely publicized.

  • Vote for this question0
  • Downvote this question0
Anonymous's avatar
Nov 3, 2021 - 19:58

Why do you not add platform screen doors to the platforms to protect passengers and objects from trains?
By doing that, You're just making the dangerous on purpose for blind passengers to fall onto tracks because of loss of vision & since the trains will on run Automatic underground, there's more than a 50% chance passengers will fall & be crushed

  • Vote for this question3
  • Downvote this question1
Metrolinx's avatar

Metrolinx
Nov 19, 2021 - 10:39

Your concern has been brought up by the accessibility committees (within Metrolinx and TTC) and this issue is being monitored. Potential solutions are being evaluated. However, at this time we have no additional information.

 

  • Vote for this question0
  • Downvote this question0
Anonymous's avatar

At what point should we expect Gilgorm Road to reopen? Will all three Chaplin station entrances have to be completed first or will it reopen once the primary station entrance is complete?

  • Vote for this question3
  • Downvote this question1
Metrolinx's avatar

Metrolinx
Nov 9, 2021 - 17:25

Gilgorm Road is expected to reopen in mid-2022; this schedule is independent from the completion of all three station entrances. Restoration works on Gilgorm Road will take place prior to the road reopening.

  • Vote for this question0
  • Downvote this question0
Anonymous's avatar
Nov 5, 2021 - 09:57

At peak hours and off-peak hours, how will frequency compare to subway service?

  • Vote for this question3
  • Downvote this question1
Metrolinx's avatar

Metrolinx
Nov 9, 2021 - 16:19

Service on the Eglinton Crosstown LRT will be operated by TTC as Line 5. Frequency of service and operating hours will be determined by the TTC Service Planning department.

The 76 light rail vehicles (LRV) can hold 163 passengers each, and reach a top speed of 80 km/h underground and 60 km/h at street level.

For more information about future service visit www.ttc.ca.

  • Vote for this question0
  • Downvote this question0
Anonymous's avatar

Anonymous
Nov 5, 2021 - 18:20

Why does the bike lane only go from Duplex to Oriole Parkway? Will there be more?

  • Vote for this question2
  • Downvote this question0
Metrolinx's avatar

Metrolinx
Nov 9, 2021 - 16:20

There will be more - road restoration at each station site will include landscaping, new sidewalks and curbs, and cycling infrastructure. The Duplex to Avenue section of the City of Toronto's Eglinton Connects Streetscape and Cycle Track design plan is being implemented by our project's constructors as an example section. The areas between stations will be built by City of Toronto.

More information about the City of Toronto's plans can be found on their website: https://www.toronto.ca/community-people/get-involved/public-consultation...

  • Vote for this question0
  • Downvote this question0
Anonymous's avatar

Anonymous
Nov 7, 2021 - 00:16

when are u going to install tapestry on the south station wall at Mount Dennis station ?

  • Vote for this question2
  • Downvote this question0
Metrolinx's avatar

Metrolinx
Nov 10, 2021 - 17:24

The tapestry on the south station wall at Mount Dennis is expected to be installed and completed by mid-December. On the north side of the station wall an art installtion will be installed in early 2022.

  • Vote for this question0
  • Downvote this question0
Anonymous's avatar

Anonymous
Nov 3, 2021 - 19:34

Did you completed all elevators between Mount Dennis & Avenue stations?
If no, how many did you install so far?

  • Vote for this question1
  • Downvote this question0
Metrolinx's avatar

Metrolinx
Nov 11, 2021 - 16:28

Elevators from Mount Dennis to Oakwood Stations are largely completed, with minor architectural and commissioning works ongoing. Framing for the elevators between Cedarvale and Avenue Stations are largely complete within the station box, and framing works will be ongoing at the Main Entrances of these stations through 2021. Commissioning of the elevators from Cedarvale – Avenue Stations will take place at most stations in early 2022

  • Vote for this question0
  • Downvote this question0
Anonymous's avatar

Anonymous
Nov 5, 2021 - 13:52

How will Oakwood station reach building construction completion by
the end of this year if glass escalators, signage and the 1 elevator have not been installed yet at the buildings?

  • Vote for this question1
  • Downvote this question0
Metrolinx's avatar

Metrolinx
Nov 9, 2021 - 16:21

The completion of architectural works within the station box and entrances, as outlined in the presentation deck, includes items such as final escalator and elevator installation, glass and glazing work, and signage. These are expected to be complete by the end the year.  

  • Vote for this question0
  • Downvote this question0
Anonymous's avatar

Anonymous
Nov 5, 2021 - 14:17

We've not been shown Forest Hill station's Main entrance

  • Vote for this question1
  • Downvote this question0
Metrolinx's avatar

Metrolinx
Nov 9, 2021 - 16:27

You can follow us on Twitter (@CrosstownTO) and Instagram (@Eglinton_Crosstown) to see the latest  photos and updates as they become available.

  • Vote for this question0
  • Downvote this question0
Anonymous's avatar

Anonymous
Nov 5, 2021 - 14:18

when are you going to install elevators for Chaplin station

  • Vote for this question1
  • Downvote this question0
Metrolinx's avatar

Metrolinx
Nov 9, 2021 - 16:34

The elevator between platform and concourse level at Chaplin Station is currently being installed - framing is already complete. The elevator from concourse to street level at Chaplin's Main Entrance will be installed in the next few months - likely 2022. Commissioning of the elevators will also take place in early 2022

  • Vote for this question0
  • Downvote this question0
Anonymous's avatar

Anonymous
Nov 5, 2021 - 14:25

Did you complete both two elevators at Avenue station?

  • Vote for this question1
  • Downvote this question0
Metrolinx's avatar

Metrolinx
Nov 9, 2021 - 16:35

The elevators at Avenue Station are mostly complete, with only minor glazing works remaining. Commissioning of the elevators will take place in early 2022.

  • Vote for this question0
  • Downvote this question0
Anonymous's avatar

Anonymous
Nov 5, 2021 - 14:32

what's so important about wet utility
installations on Eglinton Avenue
West and Hollis Street

  • Vote for this question1
  • Downvote this question0
Metrolinx's avatar

Metrolinx
Nov 10, 2021 - 17:26

The wet utilities being installed on Hollis Street will support the capacity of passengers using the infrastructure at Mount Dennis Station and the Railway Corridor. This work will tie in the stations connections to the main system as well as replacing old lines in the residential area.

  • Vote for this question0
  • Downvote this question0
darkcondor78's avatar
Nov 5, 2021 - 22:33

Passing along Eglinton outside the Fresh Co supermarket, I see the shelter rooftop of the future Caledonia station TTC bus way being formed. I know it will be completed and the main entrance by next year. Will the waiting area have heat for the winter?

  • Vote for this question1
  • Downvote this question0
Metrolinx's avatar

Metrolinx
Nov 10, 2021 - 16:11

The bus shelter/waiting area at Caledonia will not have heat in the winter.

  • Vote for this question0
  • Downvote this question0
Anonymous's avatar

Anonymous
Nov 7, 2021 - 00:18

if Keelesdale station is largely complete, then where's its bicycle parking?

  • Vote for this question1
  • Downvote this question0
Metrolinx's avatar

Metrolinx
Nov 10, 2021 - 16:06

Keelsedale has bicycle parking located within the bus loop.

  • Vote for this question0
  • Downvote this question0
Anonymous's avatar

Why don't all the other stations get the fancy nice eglinton connects finishings? I guess metrolinx executives take care of the areas they live in only while everyone else gets poorer street level finishings.

  • Vote for this question2
  • Downvote this question1
Metrolinx's avatar

Metrolinx
Nov 9, 2021 - 16:36

The section of the City of Toronto's Eglinton Connects Streetscape and Cycle Track design plan that is being implemented by our project's constructors at Avenue Station is an example section. The remaining areas between stations will be built by the City of Toronto.

More information about the City of Toronto's plans can be found on their website: https://www.toronto.ca/community-people/get-involved/public-consultation...

  • Vote for this question0
  • Downvote this question0
Anonymous's avatar
Nov 7, 2021 - 06:44
  • Vote for this question1
  • Downvote this question0
Metrolinx's avatar

Metrolinx
Nov 9, 2021 - 16:37

The project is scheduled for completion in 2022. 

  • Vote for this question0
  • Downvote this question0
Anonymous's avatar

Metrolinx committed to post the east open house by 7 pm November 9. It is still not posted. Can you please explain why there is a delay in doing something you already committed to? I understand every single project is delayed but cmon at least post the town hall material on time.

https://www.metrolinxengage.com/en/eglintoncrosstown

  • Vote for this question1
  • Downvote this question0
Metrolinx's avatar

Metrolinx
Nov 10, 2021 - 10:10

Apologies for the delay, we had techincal issues last night. You can view the East presentation  now: https://www.metrolinxengage.com/en/eclrteastvohfall2021

  • Vote for this question0
  • Downvote this question0
Anonymous's avatar

Anonymous
Nov 4, 2021 - 19:15

The photo you used for Oakwood station platform in the Presentation came from 2 months ago.
Can you us the actual photo of the platform as it is right now?

  • Vote for this question2
  • Downvote this question2
Metrolinx's avatar

Metrolinx
Nov 9, 2021 - 16:41

You can follow us on Twitter (@CrosstownTO) and Instagram (@Eglinton_Crosstown) to see the latest  photos and updates as they become available. We're hoping to have some new photos to share within the next week or so.

  • Vote for this question0
  • Downvote this question0
Anonymous's avatar

And will transferring from the subway function like a subway-to-subway transfer, i.e. you won’t have to use your presto card during the transfer?

  • Vote for this question2
  • Downvote this question2
Metrolinx's avatar

Metrolinx
Nov 9, 2021 - 16:38

Service on the Eglinton Crosstown LRT project will be operated by TTC as Line 5, as such fares and payment will be determined by TTC. For more information visit www.ttc.ca. 

  • Vote for this question1
  • Downvote this question0
Anonymous's avatar
  • Vote for this question2
  • Downvote this question2
Anonymous's avatar

Anonymous
Nov 5, 2021 - 13:42

You cannot just show the public in maps that Caledonia station will connect with GO Transit's Barrie line and yet you don't build the GO platform

  • Vote for this question2
  • Downvote this question2
Anonymous's avatar

Anonymous
Nov 5, 2021 - 13:43

In previous meeting you said that road restoration will take place in summer this year at Fairbank station. But since it's November, traffic at Dufferin & Eglinton is still in two-lane traffic.

  • Vote for this question1
  • Downvote this question1
Metrolinx's avatar

Metrolinx
Nov 10, 2021 - 16:03

Road restoration at Fairbank was completed in November 2021.  The lane reductions are currently in place to facilitate sidewalk and curb restoration works. After this is completed one lane of traffic in each direction will be maintained for construction staging and deliveries.  Final asphalt pours are expected to take place in May of 2022 after which all lanes will be reinstated.

  • Vote for this question0
  • Downvote this question0
Anonymous's avatar

Anonymous
Nov 5, 2021 - 14:14

at Cedarvale station, when will you intall escalators between the upper councourse and the lower concourse?

  • Vote for this question0
  • Downvote this question0
Metrolinx's avatar

Metrolinx
Nov 11, 2021 - 16:29

Two escalators between the upper and lower concourse are installed. Another set of two will arrive later this month for installation; marking the completion of escalator installations between these two levels.  

  • Vote for this question0
  • Downvote this question0
Anonymous's avatar
Nov 5, 2021 - 14:29

What percentage is the GO and UP Exprsss platform complete at Mount Dennis ?

  • Vote for this question0
  • Downvote this question0
Metrolinx's avatar

Metrolinx
Nov 10, 2021 - 17:29

100% of the structural work is complete. 70% of the architectural work is complete on the west and centre GO and UP Express platforms.  The east platform construction will commence in 2022.

  • Vote for this question0
  • Downvote this question0
Anonymous's avatar
Nov 5, 2021 - 18:56

When is work scheduled to start for the Barrie Go Line and when is Caledonia scheduled to begin service?

  • Vote for this question1
  • Downvote this question1
Anonymous's avatar

Will the street blocks / construction continue all the way until opening late next year?

  • Vote for this question0
  • Downvote this question0
Metrolinx's avatar

Metrolinx
Nov 12, 2021 - 14:29

The main focus going into spring will be road restoration across Eglinton Avenue. By in mid-2022, you should start to see things looking complete at street level at the majority of locations. That said, areas of construction fencing and periodic road/sidewalk occupation will still be required throughout 2022 as works wrap up.

  • Vote for this question0
  • Downvote this question0
Anonymous's avatar

I hope the train on the east side of Eglinton will start running soon. Thanks!

  • Vote for this question0
  • Downvote this question0
Metrolinx's avatar

Metrolinx
Nov 11, 2021 - 09:12

The project is still currently tracking for completion in 2022, but a specific month or date has not yet been announced. Operation will begin only once the entire line is complete.

  • Vote for this question0
  • Downvote this question0
Anonymous's avatar

It was supposed to be up from 7:00 and 3 hours later there is nothing

  • Vote for this question0
  • Downvote this question0
Metrolinx's avatar

Metrolinx
Nov 10, 2021 - 10:10

Apologies for the delay, we had techincal issues last night. You can view the East presentation now: https://www.metrolinxengage.com/en/eclrteastvohfall2021

  • Vote for this question0
  • Downvote this question0
Anonymous's avatar

Anonymous
Nov 10, 2021 - 11:25

Will both underground stations & surface stops have transfer machines?

  • Vote for this question0
  • Downvote this question0
Metrolinx's avatar

Metrolinx
Nov 12, 2021 - 14:30

The completed Eglinton Crosstown LRT will be operated by TTC as Line 5. Every station and at-grade stop platform will be equipped with PRESTO fare machines, including ticket validator machines (SFTP), among others. For TTC fare and PRESTO card information, please visit www.ttc.ca and www.prestocard.ca.

  • Vote for this question0
  • Downvote this question0
Anonymous's avatar
Nov 5, 2021 - 13:32

You didn't show us photos of the platforms at Caledonia, Cedarvale, Forest Hill & Chaplin station

  • Vote for this question2
  • Downvote this question4
Metrolinx's avatar

Metrolinx
Nov 9, 2021 - 16:39

To view the latest information and construction progress photos from across the project, please check out the Presentation Material page of our website: http://thecrosstown.ca/news-media/whats-new/presentation-materials

You can also follow us on Twitter (@CrosstownTO) and Instagram (@Eglinton_Crosstown) to see the latest photos and updates as they become available.